Topic: | Hammersmith Bridge won't be fully open until 2026 | Forum Home |
Posted by: | Adrian Pearce | |
Date/Time: | 29/10/20 09:26:00 |
There was a public Zoom session last night for 1000 people. Baroness Vere explicitly stated that by the current estimates, it will be up to "six and a half years" from now before Hammersmith Bridge is expected to fully reopen to road traffic, including buses. Other lines No chance of any kind of temporary bridge Ferry could start in Spring. Possible that 4 months after that limited pedestrian access. Better pedestrian access 7 months later than that. But will be a further 21 months before full pedestrian access and 30 months after that before buses and cars are back https://www.hammersmithbridge.org.uk/n/n101/public-meeting-with-hammersmith-bridge-taskforce |